Construction Timeline

Pre approval finance applied - 01/11/2012
Tender request - 15/11/2012
Pre approval finance granted - 19/11/2012
Tender Presentation & acceptance - 06/12/2012
Variation 1 (Client Check Plan Changes) received - 14/01/2013
Variation 1 revised - 18/01/2013
Request increase to pre approved finance amount - 31/01/2013
Pre approval finance increase accepted  - 08/02/2013
Variation 1 revised - 27/02/2013
Variation 1 revised - 04/03/2013
Variation 1 signed - 05/03/2013
DA Preparation fee paid - 10/04/2013
DA (Construction) submitted - 23/04/2013
DA (Demolition) submitted - 29/04/2013
Tile Selection - 29/04/2013
Variation 2 (Tile Selections) received - 30/04/2013
Internal Selection -21/05/2013
Tile Selection - 21/05/2013
Variation 2 revised - 22/05/2013
Variation 2 signed - 23/05/2013
DA (Demolition) approved - 04/06/2013
Variation 3 (Colour Selections) received - 06/06/2013
Variation 3 revised -  14/06/2013
Variation 3 signed - 15/06/2013
Variation 4 (Amended Tile Selections) received - 19/06/2013
Variation 4 signed - 20/06/2013
DA (Construction) approved - 21/06/2013
Electrical appointment - 25/06/2013
HIA building contract received - 25/06/2013
Variation 5 (Internal Changes) received - 28/06/2013
Variation 5 signed - 29/06/2013
Variation 6 (Council Conditions) received - 16/07/2013
Variation 6 signed - 17/07/2013
CC Plans signed & applied - 24/07/2013
Variation 7 (Electrical Selections) received - 25/07/2013
Variation 7 revised - 26/07/2013
Variation 7 signed - 26/07/2013
Finance application - 26/07/2013
CC approved - 31/07/2013
Construction Plans received - 09/08/2013
Construction Plans signed - 12/08/2013
Demolition commenced - 12/08/2013
Variation 8 (Provisional Allowance) received - 13/08/2013
Variation 8 signed - 14/08/2013
Demolition completed - 15/08/2013
Unconditional finance approval - 27/08/2013
Final kitchen plans received - 29/08/2013
Loan Docs signed - 13/09/2013
Loan settled - 27/09/2013
Builders Commencement Letter - 30/09/2013
Slab invoiced - 29/10/2013
Slab progress payment - 30/10/2013
Frame invoiced - 18/11/2013
Frame progress payment - 25/11/2013
Final kitchen plans revised - 03/12/2013
Final kitchen plans signed - 04/12/2013
Brickwork invoiced - 10/01/2014
Brickwork progress payment - 13/01/2014
Independent Frame Inspection - 20/02/2014
Internal Linings invoiced - 11/03/2014
Internal Linings progress payment - 17/03/2014
Fix-out invoiced - 21/03/2014
Fix-out progress payment - 01/04/2014
Independent Final Inspection - 02/05/2014
Rawson Final Inspection - 06/05/2014
Practical Completion Inspection - 08/05/2014
Practical Completion invoiced - 09/05/2014
Practical Completion payment/Handover - 26/05/2014
Downlights installed - 31/05/2014
Interim Occupancy Certificate - 03/06/2014
Flooring laid - 11/06/2014
Driveway completed - 23/06/2014
Plantation Shutters installed - 25/06/2014