Another take on the build progress, this time from the rear.

Demolition - 07/09/2013

Cut & Fill - 12/09/2013

Piers - 11/10/2013

Frames - 09/11/2013

Brickwork - 27/11/2013

More Brickwork - 26/12/2013

Backyard covered in weeds

This is the view standing from the laundry door.



Roof - 06/02/2014

Almost there - 18/02/2014

Door - 12/03/2014


The strange thing here was when the council approved the plans, the rain water tank was moved. It was supposed to be behind the house, but it's now located on the side of the house. The only thing left at the rear will be the air conditioning unit. Going to be quite plain and bare here.