Saturday 8 March 2014

Build Progress


It's been about 6 months and the build is progressing along...

Cut & Fill - 09/09/2013

Piers - 11/10/2013

Slab - 15/10/2013

First progress payment after the slab was completed.

Frames - 30/10/2013

More frames - 06/11/2013

Second progress payment when the frames were done. Was literally two months into construction and we've already paid for 50% of the build. House does not look like it's half done at all.

Brickwork - 14/11/2013

Pillars - 26/12/2013

Third progress payment when the brickwork was completed. It's starting to look like a home now.

Roof - 18/02/2014


Cedar Cladding - 02/03/2014

Door - 12/03/2014

Exterior is pretty much done, most of the scaffolding is down and the front door is on.

Verandah - 05/04/2014

Scaffolding is down and the verandah is done. Though I have to talk to the SS and see why was the verandah painted black and not the same stain colour as the rest of the house. If it was a base/undercoat, shouldn't it have been white?